by haitadmin | Dec 1, 2006 | Uncategorized
Even though the security situation in Haiti has deteriorated over the past months, the IAWater team has moved forward with installations. In December, the team installed a chlorinator in Hopital Communaute Haitienne, two in Hopital Fermanthe (one in the water...
by haitadmin | Sep 1, 2006 | Uncategorized
The total number of installations is now at 18 chlorinators. In September, the team conducted an additional five site evaluations and identified 26 individual needs for chlorinators.
by haitadmin | Aug 1, 2006 | Uncategorized
Installations on ten chlorinators in the Bertin area have been completed. Update – February 2007: Bertin did not receive water until last week. Since Bertin began receiving water, they have called each of the members of the IAWater team to say how extremely...
by haitadmin | Aug 1, 2006 | Uncategorized
Chlorinators have been installed in 10 300-gallon tanks in the Bertin neighborhood of Carrefour. The International Action Clean Water Campaign team completed all 10 installations the week of August 11. A major community celebration was set for Friday in Bertin, but...
by haitadmin | Aug 1, 2006 | Uncategorized
IA CWC team finished the last of three chlorinator installations in the Tokyo neighborhood in the poor Delmas section of Port-au-Prince on August 25. These three systems will provide clean drinking water to the 20,000 residents of the Tokyo neighborhood of Cité...